Recent Stormwater Harvesting Projects
Bentleigh West Primary School Stormwater Harvesting
Posted on February 15, 2010
Location: Bentleigh West, Victoria
Start: 2009
Completion: 2009
Contract type/Services: Stormwater Harvesting Systems
Project Description
Construction of a stormwater harvesting irrigation system to irrigate school ovals. Supply and installation of above and below ground water tanks to capture 270,000litres of stormwater. All associated plumbing, electrical works and irrigation.
Targets / Performance Outcomes
Works completed to the satisfaction of BWPS
Project Images
Modular cells provide big water storage in small spaces
Posted on June 15, 2009
Modular plastic cells are an ideal solution for underground stormwater storage where space is limited.
Water infrastructure specialists JHL Civil used the Rocla eco3TM modular storage cell system to create a large underground storage facility in a small space for an industrial unit at Port Melbourne….read the full article by clicking here
Caulfield Racecourse Stormwater Harvesting Project
Posted on September 1, 2008
Location: Caulfield Racecourse, Victoria
Start: 2008
Completion: 2008
Contract type/Services: Stormwater Harvesting Systems
Project Description
Construction of a 300m3 underground water storage unit and the installation of 1km of 315mm PE pipe and a 600mm bore 35m long.
Targets / Performance Outcomes
The time management of this project was crucial with the works being conducted during Spring Carnival and the Caulfield Cup taking place the day after the last of the excavated material was compacted and returned to its original state.
Click here to read the feedback from Melbourne Racing’s Greg Hoath…p259-greg-hoath-letter
Project Images
Stormwater Harvesting System for Industrial Application
Posted on August 24, 2008
Installation of 10,000 litre storm water harvesting underground tank installation at factory site in Port Melbourne
Project Images:

Loy Yang B Power Station Stormwater Harvesting
Posted on May 15, 2008
Client: HRL Technology
Location: Traralgon, Victoria
Start: 2008
Completion: 2008
Contract type/Services: Stormwater Harvesting Systems
Project Description
Provision of civil and mechanical services for Storm Water Drainage Recovery project including construction of 1.5km PE pipeline and pit redesign works. Recovery of wastewater from drain pit and pumping the water to the cooling towers.
Targets / Performance Outcomes
Working in and around a large number of services
Project completed to the satisfaction of all stakeholders
Zero LTIs.
Saving approx 45 megalitres per 4 weeks
Project Images

Stormwater Harvesting for Domestic Application
Posted on April 24, 2008
JHL Civil underground water tanks are a benefit for the environment and require no footprint to your existing land.
Below is an example of a domestic installation in Brighton, Victoria:
Project Images